Problems overcome include: steep high batters made unstable due to groundwater; large flows of water and soft ground conditions.
As part of a works to construct housing, McCarthy's were employed to divert the River Ewelme and undertake drainage on the scheme.

| Client Organisation | St Modwen |
| Main Contractor | Hawk |
| Contract Value | Circa £300,000 |
| Contract Period | April - September 2016 |
| Address | Lister Rd, Dursley, GL11 4BA |