Barry Island Causeway

McCarthys were employed by VOGC as a Principal Contractor for the challenging scheme.

A ramp up from the existing car park was constructed in the extremely soft marine deposits along with an armour stone revetment and tied into the existing delicate pitched revetment.

The Works

As part of a county wide scheme to improve cycle routes Harbour Road in Barry was modified.

Client OrganisationVale of Glamorgan Council
Contract ValueCirca £360,000
Contract PeriodJanuary to April 2016
Form of Contract/td>NEC3 Short Contract
LocationHarbour road, Barry, CF62 5TQ